AZ400-Q: migrate a scheduled pipeline correctly

A Classic pipeline runs nightly at 01:00 local time. After migration to YAML, it runs at an unexpected hour. What should the team check first?

  • A) The storage-account redundancy.
  • B) YAML schedule time-zone semantics and the explicit cron/branch configuration, then validate the next scheduled run. ✓
  • C) The production NSG.
  • D) The Git author email.

Answer: B. Schedule behavior is configuration, not just copied build tasks. Migration must account for YAML’s schedule semantics and verify the result.

Why not the others: Storage, networking, and author identity do not determine pipeline schedule interpretation.