AZ400-Q: keep a roadmap connected to delivery
Leadership needs a roadmap view without a second disconnected backlog. What should the team do?
- A) Derive roadmap items from linked epics, features, and delivery work in the planning system. ✓
- B) Copy the backlog manually into slides each day.
- C) Use commit messages as the only roadmap.
- D) Delete completed work history. Answer: A. A linked hierarchy preserves one source of delivery truth. Why not the others: Manual copies drift; commits lack planning context; deletion removes evidence.